Project overview
Royal Holloway University engaged CW Pipewise following a leak on the existing 3-inch steel incoming water main running through its underground service tunnels. The installation formed part of a critical building supply and had reached a condition where substantial replacement was the most reliable long-term solution.
The works required a planned building shutdown, removal of approximately 90% of the existing steel main within the tunnel route, and installation of a new 90 mm MDPE water main. New isolation points were incorporated so that individual sections of the building could be shut down without unnecessarily interrupting the wider system.
Scope of works and delivery
Plan and carry out the shutdown
Coordinate a controlled shutdown of the building water supply before cutting into the existing main.
Replace the deteriorated steel main
Remove the majority of the existing 3-inch steel main and install a new 90 mm MDPE main along the tunnel route.
Connect and isolate sections
Form transitions between retained steel and replacement MDPE using flanged and mechanical connections. Install new gate valves in strategic directions to improve sectional isolation.
Secure and commission the installation
Route and secure the main around other live services and limited clearances. Pressure test and chlorinate the new installation before a controlled return to service.
Working within a complex tunnel environment
The replacement route passed through underground service tunnels with restricted access, low headroom and multiple existing services. The area was subject to asbestos controls, so work took place within the university’s controlled asbestos-management arrangements as well as confined-space restrictions.
Access, sequencing, material movement and the shutdown required careful planning. Pipework was removed and installed within a narrow operational corridor without compromising adjacent services. The new main was positioned to provide a clear, maintainable route while retaining access to surrounding infrastructure.
Testing, chlorination and return to service
The completed 90 mm MDPE main was pressure tested to verify the integrity of the pipework, fittings, valve assemblies and transition connections. The system was held under test for the required period and checked for pressure stability before acceptance.
The potable-water installation was chlorinated as part of commissioning. Once testing and chlorination were complete, the system was returned to service in a controlled manner, with the new isolation valves accessible for maintenance and emergency use.
Engineering outcome
The works removed the majority of the ageing steel main from this section of the university and replaced it with a fully commissioned 90 mm MDPE system. The leak was resolved, and additional gate valves gave the estates team greater control over future maintenance shutdowns.