180 mm washout main installation at Thames Water Egham

Installing and fusion welding a new washout main, tested to 10 bar ahead of a planned connection to the existing 225 mm main.

Installation works for the new 180 mm HDPE washout main at Thames Water Egham.
Installation works for the new 180 mm HDPE washout main at Thames Water Egham.
Client / site
Thames Water sewage treatment works, Egham
Asset
180 mm HDPE washout main
Work
New main installation and pressure testing

Project overview

CW Pipewise was instructed to install a new 180 mm HDPE washout main at a Thames Water sewage treatment works in Egham. The pipeline formed part of an upgrade to the site’s washout arrangement. It was installed as a new dead main so the full run could be constructed, fusion welded and tested before connection to the operational network.

The new line was laid through an open-cut trench across a congested utility area, using electrofusion couplers and bends to achieve the required route. Once completed, the entire dead main was pressure tested to 10 bar and left ready for a planned second visit to complete the final connections onto the existing 225 mm main.

Scope of works and delivery

  1. Set out and install the new main

    The trench route was prepared and the new HDPE pipe installed to the required line and level on suitable granular bedding, maintaining clearance from existing buried services.

  2. Fusion weld the pipeline and fittings

    Pipe ends were measured, cleaned and mechanically scraped before electrofusion couplers and bends were installed. Alignment and restraint equipment maintained joint position during each programmed fusion and cooling cycle.

  3. Navigate existing site infrastructure

    The main was routed through a congested operational area containing drainage, ducts, chambers and crossing services. Suitable bends were used while retaining access to existing assets.

  4. Pressure test and prepare for tie-in

    With the new main still dead, the completed system was pressure tested to 10 bar to verify the pipework and fusion joints. It was then left ready for the second-phase connection to the existing 225 mm main.

Engineering outcome

The new 180 mm HDPE washout main was fully installed, fusion welded and successfully pressure tested to 10 bar before any connection was made to the live network. Completing and proving the pipeline in advance reduced the work required during the future shutdown and left a controlled, tested system ready for final tie-in to the existing 225 mm main.

Project stage recorded in the supplied case study: installation and pressure testing complete; final connection to the existing 225 mm main planned for a second visit.

Discuss your water mains project

Speak to CW Pipewise about repairs, replacement pipework and commercial water infrastructure.

CW Pipewise
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.